Our networks team is working constantly to improve our mobile network's coverage and capacity. Here are the planned upgrades for the coming weeks. If you're in one of the areas listed below, you may experience a partial or complete loss of mobile voice and data services between 7am and 8pm on the dates listed. After the work is complete, we are confident you will enjoy a better coverage and faster speeds on the Vodafone mobile network.

 

Site Name Site Code Area Scheduled Start Scheduled End Frequencies on Site Work Type Frequencies on Site After Work Done What change will you notice?
Central Park A2CLP Waitakere City Monday 29th June 2020 Monday 29th June 2020 G9U9U21L7L18 Battery Installation G9U9U21L7L18 NA
Okaihau N1OKI Far North Wednesday 1st July 2020 Friday 3rd July 2020 G9U9L7L18 Project Slice Upgrade G9U9L7L18 NA
Pakaraka N1PAR Far North Tuesday 30th June 2020 Thursday 2nd July 2020 G9U9L7L18L21 Project Slice Upgrade G9U9L7L18L21 NA
Whangaroa N1WGA Far North Monday 29th June 2020 Thursday 2nd July 2020 G9U9L7L18 Project Slice Upgrade G9U9L7L18 NA
Woodhill N2WDH Rodney Friday 26th June 2020 Tuesday 30th June 2020 G9U9L7L18 Project Slice Upgrade G9U9L7L18 NA
Arrowtown Basin S5ATB Queenstown Lakes Saturday 4th July 2020 Thursday 9th July 2020 G9U9 Project Slice Upgrade G9U9L7 More reliable coverage, More Capacity - Additional Layer (L7)
Bishops Bay S5BIB Queenstown Lakes Monday 29th June 2020 Tuesday 30th June 2020 U9L7 Project Slice Upgrade U9L7 NA
Cardrona Valley S5CDV Queenstown Lakes Tuesday 30th June 2020 Friday 3rd July 2020 G9U9U21L7L18L21 Project Slice Upgrade G9U9U21L7L18L21 NA
Cromwell S5CMW Central Otago Tuesday 30th June 2020 Friday 3rd July 2020 G9U9U21 Project Slice Upgrade G9U9U21L7 More reliable coverage, More Capacity - Additional Layer (L7)
Ophir S5OIR Central Otago Monday 29th June 2020 Tuesday 30th June 2020 G9U9L7 Project Slice Upgrade G9U9L7 NA
Milton Township S6MTS Clutha Monday 29th June 2020 Friday 3rd July 2020 G9U9L7 Project Slice Upgrade G9U9L7 NA

 

NOTE: While every effort will be made to maintain coverage during cell site upgrade work there may be times during the work sequence where partial or complete outages to existing services are necessary. Existing services will usually be restored each evening.

 

A word about 4G frequencies

 

If your area has 4G 1800MHz or 2600MHz, you can enjoy 4G with any Vodafone approved 4G capable device. If your area only has 4G 700MHz, you need a Vodafone approved 4G phone which supports 700MHz. For the full list see http://www.vodafone.co.nz/4G